New roundabout junction at Shepperton

https://files.mutualcdn.com/careys/images/Shepperton-rundabout-works.JPG

Our team have recently completed the construction of a new roundabout at the junction of Studios Road, New Road and Squires Bridge Road in Shepperton.

  • Careys
  • Thursday 6th March 2025

Share this:-

New roundabout junction at Shepperton

This new roundabout improves the flow of traffic through this junction, making it safer than the previous junction. Our scope of works included:

- Break out and removal of the existing carriageway and replacing with
new
- New kerb lines and drainage
- Installation of a new signalised pedestrian crossing
- Installation of new signage including illuminated chevron
- New fencing to the works boundary
- Utility diversions and installation of new chambers while keeping the
network live for customers
- Installation of two large soakaways
- Soft Landscaping
- Liaison with the adjacent school and neighbours

The works were completed ahead of programme.

We'd love to hear from you, so please get in touch